The Army has canceled the Ground Combat Vehicle (GCV) solicitation because the service decided, after an internal and external review, that the current Requests for Proposal (RFP) do not accurately reflect Army requirements and a changing acquisition strategy, sources tell us.
A contract for the new vehicle was very close to being awarded, we’re told. A restart of the GCV competition is expected fairly soon, a new RFP may be out within 60 days, and the Army intends to stay within the original seven year timeline to field a new vehicle.
A contentious debate has taken place among Army officials regarding the new infantry fighting vehicle’s lengthy requirements list, a debate fed by an Army and OSD staffed “Red Team” analysis which scrutinized vehicle proposals and the lethality of modern and future battlefields, as well as disagreement among leadership about the service’s GCV acquisition strategy. The new RFP will reflect the Red Team’s findings as well as the Army’s analysis of alternatives.
The proposed GCV, which is intended to replace the Army’s Bradley fleet, was getting a bit unwieldy, sources say, as builders attempted to meet the many requirements. The Army will issue a formal announcement this afternoon. Lawmakers (the few who are available in late August; more like their secretaries) were notified of the GCV cancellation this morning.
Updated: The GCV competition was cancelled so the Army can “better ensure an achievable, affordable, and timely infantry fighting vehicle,” according to an emailed Army announcement. The cancellation will result in a six month delay of the program, although the service intends to field a vehicle within seven years after a contract is awarded.
“In conjunction with the Red Team recommendations, the Army determined that it must revise the acquisition strategy to rely on mature technologies in order to reduce significant developmental risk over a seven year schedule following the initial contract award. The refined RFP will result in a vehicle that provides soldiers with critical armored protection in the modern combat environment.”
The emailed announcement says details of the specific RFP are still being finalized and the service expects to issue a new solicitation within the next 60 days.
-- Greg Grant